Why sometimes a few lines of code changes take several days of deployment. Find the answers and Code Move Strategy:-
Recently In one of my project I faced the following situation: We did a code change in trigger. Changed a string value from “Demo” to “Trial”. The code change hardy took 1 minutes. Client was aware of the changes and  time it will take so we estimated the work as 2 hour including code changes, analysis of its impact and deployment. When the developer finished deploying the code changes it took him 2 days (16+ Man-hours). Yes it is a surprise. Now let me list out the problems he faced.  
  1. Code coverage of the existing trigger was 12% (Our Company Best Practice is 85%)
  2. Code coverage of overall production org was less than 75%. Yes this is hard to believe but this do happen when we push things in production without code coverage.
  3. Existing test classes were failing in production.
  4. Trigger in production was different than in Sandbox. Yes this is also possible when we have multiple sandboxes and people do code overrides as they are competing against each others.
  5. Deployment had a narrow slot of 2 hours during which end client were not working.
  6. Batch Jobs working on the same object were preventing the Trigger to deploy.
We gave our best as a team and came up with the following strategy which changed our entire company's estimation and requirement analysis process.
strategyCode Move Strategy:
Step 1: Check the existing production code coverage by “Run All Test”.
Run_All_Test
                                                                    
Step 2: Lookout for test class failures if any.
Step 3: List out the Batch jobs running in production.
job
Step 4: Compare the code between production and sandbox before working on it. If any differences found report it to your end Client/Manager.
Step 5: Make sure if you are deploying an apex code its code coverage should be above 85%.
Code_Coverage
Step 6: Use Changeset for small size deployment with less components. Keep the changeset names in a well defined order.